Short answer
A tender or supply contract can require up to four guarantees, one for each stage of the deal. Each is a bank’s undertaking to pay your client a fixed amount if you fail a specific obligation. This guide explains what you will be asked for, what to check before you sign and how issuance works.
Key points
- A contract can require up to four guarantees: tender (bid bond), performance, advance payment, and warranty or retention.
- A demand guarantee is independent of the contract: the bank pays if the demand matches the terms of the guarantee, without investigating whether you actually failed.
- Under URDG 758 the beneficiary must state in what respect you are in breach, and the bank has five business days to examine the demand.
- Negotiate the wording before you sign the contract: rules, a fixed expiry date, reduction, effective date, demand documents and who may issue.
- When the buyer accepts only a local bank, your issuer sends a counter-guarantee and the local bank issues the guarantee: expect a second set of fees and a longer timeline.
The four guarantees, stage by stage
| Guarantee | What it secures | Typical amount | Usually runs until |
|---|---|---|---|
| Tender guarantee (bid bond) | You maintain your bid and sign the contract if you win | 1–5% of the bid value | Award and signature of the contract |
| Performance guarantee | You deliver as the contract requires | 5–10% of the contract value | Delivery or provisional acceptance |
| Advance payment guarantee | The down payment is repaid if you do not deliver | 100% of the advance received | The advance is absorbed by deliveries |
| Warranty or retention guarantee | Defects are fixed during the warranty period | 5–10% of the contract value | End of the warranty period |
These ranges are market practice. Your contract sets the real figures.
What “on demand” really means
A demand guarantee is independent of the contract. The bank does not investigate whether you actually failed. It pays if the demand matches the terms of the guarantee.
Under URDG 758, the ICC rules for demand guarantees, the beneficiary must state in what respect you are in breach. The bank then has five business days to examine the demand. No court, expert or arbitrator is involved unless the wording says so.
This is why the wording matters more than the price. A cheap guarantee with loose wording is the expensive one.
Six points to check before you sign the contract
- The rules. URDG 758 for a demand guarantee, ISP98 for a standby letter of credit. If the text is silent, local law fills the gaps.
- The expiry. Ask for a fixed calendar date. Refuse “valid until released by the beneficiary”: you would pay fees with no end date and your security would stay blocked.
- The amount and its reduction. An advance payment guarantee should reduce as you ship or invoice. A performance guarantee can reduce at provisional acceptance.
- The effective date. An advance payment guarantee should become operative only when the advance reaches your account.
- The demand documents. A written statement of breach is the minimum. Where you have leverage, add a copy of the default notice sent to you.
- Who may issue. “A first-class bank”, a bank in the buyer’s country or a named list: this line decides the structure, the cost and the timing.
These points are negotiable before signature. After signature, the guarantee must follow the contract.
Direct guarantee or local bank?
Some buyers accept a guarantee issued directly by a foreign bank. Many public buyers in North Africa, the Middle East and parts of Asia accept only a guarantee from a bank in their own country.
In that case your issuer sends a counter-guarantee to a local bank, and the local bank issues the guarantee. Expect four consequences:
- A second set of fees, charged by the local bank.
- Local law and a local template, often not negotiable.
- A longer timeline, because two institutions review the text.
- A counter-guarantee that expires later than the guarantee itself, so your security stays committed longer.
Plan also for “extend or pay” demands. The beneficiary asks for an extension and, if it is refused, calls the guarantee.
Have a real transaction that needs an instrument? Tell us about it in two short steps. We review the operation and reply within 24 hours on business days with the options and next steps.
Discuss your transactionWhat the issuer will ask from you
- The signed contract or the tender documents, with the guarantee clause and any imposed template.
- Company documents: registration, shareholders, directors and their identification.
- Recent financial statements and your record on similar contracts.
- The beneficiary’s full details and bank.
- Security. The issuer takes a risk on you and decides what it needs to cover it.
No serious institution issues a guarantee without assessing the company behind it. See our documents checklist.
How long it takes
Tender deadlines do not move, and a late guarantee means a rejected bid. Start when you decide to bid, not when the bid is ready.
As an order of magnitude, allow two to three weeks from a complete file for a direct guarantee. Add one to two weeks when a local bank must issue. The usual sequence is review of the wording, review of your file by the issuer, approval of the draft by the beneficiary, then issuance by SWIFT MT760.
Five mistakes we see most often
- Signing a contract with an imposed template that no issuer has reviewed.
- Accepting a guarantee with no fixed expiry date.
- Letting an advance payment guarantee take effect before the advance is received.
- Overlooking the clause on who may issue.
- Requesting the guarantee a few days before the tender closes.
Have a tender or contract that requires a guarantee?
Send us the guarantee clause and the template, if one is imposed. We will tell you what looks feasible, what is missing and which points to raise with your client. The initial review is not an approval: the final decision belongs to the issuing institution.
Discuss your transaction · Related: Contractual guarantees · Guide: bank guarantee
Sources
Star Alliance Consulting editorial team · Updated 11 November 2026